News & Events

News & Events

Filter by Topic

Filter by Year

  • New Neilson

First Look: Inside the New Neilson Library

See gorgeous new footage of the interior of the new Neilson Library.

The video shows a number of views and spaces not yet seen by the public, including reading rooms, study areas, the rooftop terrace, and more.

 

Contact

Ask Us!

  • New Neilson
    News

First Look: Moving Books into the New Neilson Library

On December 14, 2020, the W.B. Meyers company and Smith Libraries staff began preparing to pack up books in the Five College Annex. The Annex, located in Hatfield, has been holding hundreds of thousands of Smith College books while the Neilson Library was under construction. On December 29, the first books began returning to the Neilson Library. Here are some first-look photos of the book moving process.

  • New Neilson

Get a sneak peek at the Neilson Library renovation as of fall 2020!

Get a sneak peek at the Neilson Library renovation as of fall 2020!

  • New Neilson

Live Edge Furniture in Production for Neilson Library

In June 2017, a large elm tree in front of Neilson Library was taken down. The utility rerouting required for the new library construction impacted the root base of the tree and it was removed as a precaution. The wood from the tree, however, will live on as eight unique pieces of furniture in the new Neilson Library.

Read more...

  • New Neilson

Neilson Library Construction Update, July 27, 2020

The first stages of site work outside of the Neilson Library construction perimeter will begin July 27, 2020. Existing light poles on the walk from the entrance to Bass Hall, passing in front of Burton and up to Chapin Lawn will be replaced with the new poles and fixtures. The walks will be passable.

  • New Neilson

Neilson Library Construction Update, May 20, 2020

On Monday, May 18, 2020 per order of the Governor, the Commonwealth reduced restrictions on construction activity within its borders. For the past six weeks, the project team has moved from full shutdown to a cautious ramping up of activity and has implemented new protocols for the protection of construction workers at the Neilson Library and Alumnae Gym work sites. The worker safety protocols put in place, and the essential work completed to protect the building, will allow construction progress to approach productivity levels from the pre-COVID 19 era.

Read more...

  • New Neilson
    News

Important Update On The Neilson Library Project, April 3, 2020

In order to support worksite health and safety, construction has been discontinued on the Neilson Library project including Neilson Library and Alumnae Gym. A preliminary construction restart date of May 4, 2020 has been set, but conditions will be reassessed and there is a significant chance that the closure will be extended.

Read the letter to the Smith community about the Neilson Library project.  

  • New Neilson

Neilson Library Construction Update, March 10, 2020

Construction activity is planned over spring recess that is outside of the Neilson construction perimeter and will impact access into Wright Hall and Wright Hall parking, including the handicap parking at the building. The work is scheduled to begin on Monday, March 16 and continue through Friday, March 20. Accessible access into Wright Hall will be maintained at all times and required egress routes will be provided. Accessible pedestrian access will also be maintained on paths and drives around the building without major detours and handicap parking will be relocated to within 200 feet of the building entrance.

Read more...

  • New Neilson

Neilson Library Construction Update, March 3, 2020

The mood is upbeat at the construction site with the weather improving and work for the most part unencumbered by the elements. The building exterior is approaching completion as masons install the limestone blocks under the staging wraps and roofers complete the slate tile on the 1909 Neilson sloped roofs. The contractor expects to have the entire exterior facade completed in about two months.  

Read more...

  • New Neilson

Neilson Library Construction Update, December 4, 2019

The contractor will be working a second shift at the library for the next two weeks or so. Shawmut Construction will keep a project manager on site from 3 p.m. until 11 p.m. to supervise a crew that will be applying spray foam insulation to the interior face of the 1909 masonry walls. This means that the construction lights inside the building will be on until 11:30 p.m. This work is being done in the evening to not impact the other trades who are working in the building during the day hours and to help keep the project moving forward on schedule. 

  • 1 of 5